At the Morley Village Council meeting on May 13, 2024, a resident asked why the millpond had stayed low for so long. Village President Henry Petersen explained that the village had been doing spring drawdowns in recent years to handle spring rains. The same subject has come up at council meetings for two and a half years since then. It led to sediment testing, a state go-ahead to seek bids, a vote to apply for $5 million in federal funding, a summer drawdown and, this August, a crowd that filled the Morley Stanwood High School gym.
Most of that work points to one repair that hasn't been built yet. In March the council approved the first phase of engineering for it and heard prices for four more, two of them tied to specific parts of the dam.
The Dam and the Pond Belong to the Village
The village's 2024–28 parks and recreation plan lists the Little Muskegon River impoundment as a fishing area and says the Village of Morley owns the dam. Frank Deyo Dam Park covers about 1.5 acres, including the dam itself, and has a boat launch and a popular fishing spot. Upstream on the river, Latimer Park has a boat ramp, pavilion, playground and picnic area. The pond also gave Celebration on the Pond its name. That's why the repair matters to people who never put a boat in the water.
The dam was inspected on May 31, 2024. At the June 10, 2024 meeting, before the written report arrived, Petersen passed along what the inspector had told him. The inspector wanted the village to keep up the pond drawdowns and the gate repairs. He said the gates had been repaired in 1992 but should have been done differently. He also said keeping the water low in spring would not increase weeds, but he would like to see it higher in spring than it had been. In short, the gates were the problem to fix, and the drawdowns were how the village managed the pond until the fix happened.
From a Sediment Sample to a State Go-Ahead
In 2025 the work moved from the gates to the pond bottom. At the January 2025 meeting, Austin Korpal and Steve Weed said they would ask dam engineers for a price on measuring sediment. In April, Korpal brought a bid from Cliff Young for $11,000. The council wanted more bids and suggested contacting PLM and an engineer at Fleis & VandenBrink. By September, Korpal had the sediment results.
The November 10, 2025 minutes record that the state environmental agency, EGLE, had approved moving forward with bids for the dam repair. The council also planned to check whether the village still had the old steel slabs used to block the spillways.
On March 9, 2026, the council made its two biggest decisions so far. Korpal asked to apply for $5 million in federal funding to dredge the pond, repair the dam and possibly build a boardwalk. He noted the village would not have to put up a matching amount. The motion carried. At the same meeting, the council approved the first phase of work by GEI Consultants.
GEI's Price List, Phase by Phase
The March 9 minutes list GEI's scope for the dam with a price for each phase. The council approved the first phase. The other four were priced at the same meeting but not approved:
- Initial site visit, $6,500, and site design, $14,000. This $20,500 phase was approved in March.
- Site visit and design for the deteriorating concrete, $14,500.
- Site visit and design for erosion on the upstream slope, $11,700.
- Bid support, $23,000.
- Construction oversight, $50,000.
Together those engineering phases come to $119,700, before any contractor bid for the construction itself. Two of the priced phases name specific parts of the dam, the concrete and the upstream slope, in addition to the gate work the 2024 inspector raised.
The Summer Drawdown That Paused in July
The repair was set to start this summer. The May 11, 2026 minutes say the village planned to draw down the pond to fix the dam. At the same meeting, the council approved a $5,925 bid for a new 16-by-33-foot boat launch. At the June 8 meeting, the village reported that its permit had been issued and that the drawdown would begin Monday, June 15.
Plans changed within a month. At the July 13 meeting, Korpal told the council the repair was on hold until later in the year. He said it would need cofferdams, the temporary walls that keep water out of a work area, and more money. The council voted to start raising the pond right away, on a motion by Petersen seconded by Weed. For anyone who fishes, launches a boat or walks at the pond, the date the repair restarts is the one to watch, because this summer's plan started with lowering the water.
An August Hydropower Pitch at the Same Dam
In August, a separate idea came to the same dam. The Daily News in Greenville reported on August 10 that Boston-based GenH had proposed a "data services facility" at Frank Deyo Dam, powered by what the company called "clean hydropower." The company's memo described siphons that carry water around existing structures, with turbines and generators on land or canal sites. It said the approach avoids permanent changes to the dam or the river. GenH's page for dam owners describes land-lease payments for access to water rights and installation at the dam. Its home page says the company funds, installs and operates its systems at no cost to dam owners.
The council first scheduled the discussion for Deerfield Township Hall. The crowd ran out the door and into the parking lot, so the meeting was postponed, The Daily News reported under the headline "No dam data center here." On August 18 the meeting moved to the Morley Stanwood High School gym. The village minutes count about 250 community members there. GenH's presentation of a "Next Generation Hydropower opportunity" began at 7:39 p.m., public comment ended at 9:34 p.m. and the meeting adjourned at 9:38. A Holland Sentinel column put the facility at 600 square feet.
Gander Newsroom's statewide directory, updated November 10, still lists the Morley project as proposed. It reports that company officials said no formal proposal exists yet. It also reports that Village President Austin Korpal said he'll "go with the people," which leaves a moratorium as an option.
The council's minutes record the GenH presentation separately from the dam repair. The "Millpond & Dam" section of the August 18 minutes reads "none," and the same section of the September 14 minutes is blank. The latest repair entry under that heading is still the July note about cofferdams and more money.
Following It From Here
The council posts its approved minutes on the village's meeting minutes page, and the "Millpond & Dam" heading is where the repair shows up. The next steps to look for there are approval of a later GEI phase, a construction bid or a new drawdown date.
The village's next public event is at Kinney Park. On December 4, Morley hosts "A Small Town Christmas" from 6 to 8 p.m. at Kinney Park, with cookie decorating, carriage rides, a tree lighting, Santa Claus, hot chocolate, fire rings and s'mores.
If you own a home on or near the millpond, or you're thinking about property along the Little Muskegon, a dam project can change how a lot looks and how it's used from one season to the next. Laura Veersma and the Big Rapids Realty team work with buyers and sellers in Morley and across Mecosta County, and we're glad to talk through what you're seeing at the water and what it means for your plans. Visit our Morley neighborhood page or reach out anytime. Contact Us.